Distribution Systems Testing, Application and Research


Home > Research Activities: Research Summary - Wye-Delta Overhead Banks
Research Summary
Research Summary
Project Listing
Software Products
Obtaining Software

Wye-Delta Overhead Banks

Switching overhead wye-delta three-phase transformer banks phase-by-phase can create overvoltage problems and fail arresters or transformers. This topic was investigated by DSTAR research, yielding guidelines on switching practices, overvoltage protection, and the capability of arresters to survive these overvoltages. This research has even discovered a previously unreported overvoltage phenomenon, creating extreme overvoltages magnitudes, which is the apparent cause for numerous transformer failures reported in the field.  An example of this newly discovered overvoltage phenomenon is shown below. 

sdni.jpg (42155 bytes)

Phase to ground voltage on a bank of  three 25 kVA low-loss poltop distribution transformers connected in wye-delta.  One phase was previously closed, the second primar phase was closed at 21 ms on the plot shown below

 

Home | About DSTAR | DSTAR Objectives | DSTAR Organization | History of DSTAR | DSTAR Members | DSTAR Leadership
How to Join DSTAR | Obtaining Products | Research Activities | Research Summary | Project Listing | Software Products | Obtaining Software | Members Area